Use
You can create a scheduling agreement as follows:
- Manually
You enter all data on the scheduling agreement manually.
- Using the referencing technique
As reference document (the document you copy from), you can use:
- Purchase requisitions
- RFQs/quotations
- Other scheduling agreements
You can also combine the two options. For example, you can copy data from a reference document and then change or supplement this data as required.
If you wish to set up a scheduling agreement not with one of your vendors but with one of your own plants, you should create a stock transport scheduling agreement (scheduling agreement for longer-distance stock transfers).
Prerequisites
Before you create a scheduling agreement manually, you need the following information:
Account assignment
For each item to be posted to a consumption account, you need the account assignment category and the account assignment data (for example, the number of the cost center to be charged). (See also Account Assignment.)
MPN material number
If you wish to order a material with a manufacturer part number (MPN), you need the MPN material number. See also: Manufacturer Part Number (MPN)).
Purchasing organization/purchasing group
You must assign the scheduling agreement to a purchasing organization and a purchasing group. The release (delivery schedule) must then contain the same purchasing organization as the corresponding scheduling agreement.
See also:
Creating a Scheduling Agreement Manually
Creating an Outline Agreement by Copying or Using the Referencing Technique
- Sched. Agmt. Referencing Centrally Agreed Contract...
- Administration of Scheduling Agreements
- Monitoring the Transmission of Delivery Schedules ...
- Displaying Release Docu. for Scheduling Agreement
- Determining the Agreed Cumulative Quantity
- Cumulative Quantities using SAP MM Outline Purchas...
- Messages for Scheduling Agreement Releases
- Example: Creation Profile/Creating SA Releases
- Creation Profile using SAP MM Outline Purchase Agr...
- SA Releases (Forecast or JIT Delivery Schedules) u...
- Materials Planning and Sched. Agreement Release us...
- Generating Scheduling Agreement Releases: Process ...
- Creating Delivery Schedule Lines for SA Item using...
- Defining the Firm, Trade-Off, and Planning Zones u...
- Creating a Scheduling Agreement Manually using SAP...
- Creating a Scheduling Agreement using SAP MM Outli...
No comments:
Post a Comment