Current Stock/Requirements List Overview

In the stock/requirements list, the most up-to-date development of stocks and requirements is displayed. The layout of the list on the screen is the same as that of the MRP list.

The main difference between the MRP list and the stock/requirements list is that each time the stock/requirements list is called up, the system re-reads the various MRP elements and displays the most up-to-date situation. As a result, you always see the most recent availability situation for the material in the stock/requirements list whereas the MRP list reflects the stock and requirements situation at the time the last planning was carried out and changes which have taken place after the planning date are not included.

Displaying Another Material’s Stock/Requirements List