Displaying MRP Segments Directly MRP Planning Result Evaluating MRP Lists

The MRP list can be divided into individual MRP segments according to the planning types. For storage location MRP, for example, in addition to the net requirements calculation segment, a so-called storage location segment is created for each individually planned storage location.

The net requirements calculation segment (or the net segment) also displays the part of the MRP list where net requirements calculation was carried out at plant level during the planning run. Below the storage location segment, you see the planned availability situation at storage location level.

If several segments are available in an MRP list, you can display them directly without having to search for them by scrolling. To do this, select Edit ® Next segment. You now only receive the segment for net requirements calculation (net segment). All of the other segments are suppressed. If you select this function again, the next segment is diplayed, and so on. If, for example, several storage location sections exist, then the first storage location segment is displayed and the others are suppressed. If you only want to see the net segment or the individual customer segment, select Edit ® Next segment or Ind.customer segment.


No comments:

Post a Comment

Google
 

Subscribe Here

AddThis Feed Button

Content