Subscribe

RSS Feed (xml)

Powered By

Skin Design:
Free Blogger Skins

Powered by Blogger

Displaying MRP PPC Planning Calendars

To display existing planning calendars, proceed as follows:

  1. Starting from the Material Requirements Planning menu screen, select, Master data
  2. ® Planning calendar ® Display periods.

    The initial screen for planning calendar maintenance now appears.

  3. Enter the plant of the planning calendar that you want to display.
  4. Enter the planning calendar you want to display or select,
  5. Calendar overview and choose one or more planning calendars.
  6. The screen used for maintaining the planning calendar now appears.
  7. To check the individual periods of the planning calendar, select,
  8. Periods or, Goto ® Periods.
  9. If you selected several calendars in the overview, the system now automatically displays the next planning calendar that you selected.

No comments:

Post a Comment

Google
 

Subscribe Here

AddThis Feed Button

Content