If delivery of the total order quantity is to be spread out over a certain period according to a prearranged schedule, you can enter each desired delivery date (and time if you wish) in schedule lines (e.g. 20 pcs. on 5 May 1993 at 10.00 hrs., another 20 pcs. on 6 May at 10.00 hrs., and 60 pcs. on 10 May).
You enter this data in the delivery schedule for the relevant PO item.
Procedure
- Select the desired item in the item overview.
- Choose Item ® Delivery schedule.
- Enter the delivery date (day, week, or month), the delivery time-spot, and the scheduled quantity for each delivery.
The screen for entering schedule lines for the item appears.
The section Outline Agreements with Vendors contains detailed information on the subject of delivery schedules created under scheduling agreements.
- Specifying Incoterms and Purchase Orders Shipping/...
- Incoterms and SAP Purchase Orders Shipping/Deliver...
- Units of Measure in SAP Purchase Orders
- Specifying Multiple SAP Purchase Orders Account As...
- Specifying Single Account Assignment SAP Purchase ...
- Account Assignment SAP Purchase Orders
- Creating a SAP Purchase Order With Zero Value
- Maintaining a Delivery Schedule for a SAP Purchase...
- Creating a SAP Purchase Order by Copying or Refere...
- Creating a SAP Purchase Order PO - Without a Maste...
- Creating a SAP Purchase Order - With a Master Reco...
- Creating a SAP Purchase Order Manually (Vendor Kno...
- Creating a Purchase Order using SAP
- SAP Purchase Orders Item Category
- What is Purchase Order in SAP?
No comments:
Post a Comment